Facility Updates

Dixie Fire smoke plume in background of new facility
PCS breaks ground on Quincy facility
09/22/2021
Plumas Charter School broke ground in August 2021 on their new site located at 1425 E. Main Street in Quincy.
Read More About PCS breaks ground on Quincy facility
clear
Draft plot plan
Close of loan, final facility design near
02/12/2021
Plans move forward for new Quincy facility; construction could begin as early as May.
Read More About Close of loan, final facility design near
clear
Zoning administrator hearing
Special use permit granted
12/11/2019
At a Dec. 11 hearing, the Plumas County planning director granted a special use permit to Plumas Charter School and the Central Plumas Recreation and Park District, allowing negotiations to move forward.
Read More About Special use permit granted
clear
1425 E. Main St.
Construction possibilities end at one site, begin at another
06/28/2019
PCS ends construction plans for Kelsey Lane property and begins investigation into a new facility location.
Read More About Construction possibilities end at one site, begin at another
clear
Kelsey Lane property
Survey results mean delays for new facility
05/29/2019
With site studies finally completed, results indicate new hurdles for PCS's Kelsey Lane facility project.
Read More About Survey results mean delays for new facility
clear
PCS staff meets with construction, planning, and design professionals to work on plans for new Quincy facility.
Initial planning and design meeting held
09/20/2018
PCS staff meets with construction, planning, and design professionals to work on plans for new Quincy facility.
Read More About Initial planning and design meeting held
clear
Norm Lambert uses his excavator to pull down an old building on the site of PCS's new facility.
Demolition starts on-the-ground work at new facility
09/12/2018
On-the-ground work at PCS's new Quincy facility location started with demolition of a dilapidated house. The adjacent barn will be repaired and put to use.
Read More About Demolition starts on-the-ground work at new facility
clear
PCS pine cone logo
PCS facilities committee set to interview contractors
09/05/2018
The PCS facilities committee will interview contractors who have bid on the Quincy facility project in order to inform their selection decision.
Read More About PCS facilities committee set to interview contractors
clear
Contractors walk the site with PCS Executive Director Taletha Washburn and project manager Nick Trover.
Contractors attend pre-bid meeting, walk site in Quincy
08/14/2018
Plumas Charter School's executive director and project manager host a pre-bid meeting Aug. 14 in order to present the school's new Quincy facility plans and site to interested contractors.
Read More About Contractors attend pre-bid meeting, walk site in Quincy
clear
Plumas Charter School pinecone logo
Current timeline for new Quincy facility process
08/07/2018
Based on current knowledge, this timeline lays out the upcoming steps in the process of developing Plumas Charter School's new Quincy facility.
Read More About Current timeline for new Quincy facility process
clear
Vicinity map shows where new Plumas Charter School facility will be built in Quincy, CA.
Special use permit approval and loan approval open the door to the next phase for PCS Quincy facility
08/01/2018
Accomplishment of two major milestones -- the special use permit approval and loan approval -- means Plumas Charter School can move forward with plans for new facility in Quincy.
Read More About Special use permit approval and loan approval open the door to the next phase for PCS Quincy facility
clear